San Antonio, TX · Dry utilities · TxDOT ROW
Electric and telecom utility relocations for I-35 Nex South
Relocation of approximately 5,000 feet of telecommunications duct banks and 4,000 feet of electrical duct banks within TxDOT right-of-way — a design-build delivery.
Our scope
Plans and profile construction drawings for underground dry-utility relocations by open cut, HDD bore, and conventional bores under I-35 and Loop 410, plus 3D models for the duct banks.
Obstacles & solutions
Each utility owner required a dedicated plan set, even for joint trenches. Conventional bores had to pass under a highway, hold 10-foot clearance from piers, cross a railroad perpendicularly, and keep 40-foot clearance from existing transmission poles. The team delivered signed documents in nine months.